[ Estimating Debt Service on Interim Construction Loans and Internal Capital Project Loans ]
View PDF Version
Background
The Treasurer's Office periodically issues to your School or Center updated interim interest and
internal capital project loan schedules. The principal and interest amounts shown on these schedules
should be included in your five-year budget submissions, using the specified COA segments. If you
have questions about the amounts shown on these schedules, you should contact Jeff McCray
(jmmccray@pobox.upenn.edu; 215.898.1084) for clarification or correction.
You should also feel free to contact the
Budget Office analyst assigned to your School or Center with any questions.
As you refer to the Treasurer's Office schedules, please note that the amount of
interest to be budgeted for the upcoming fiscal year for a given project depends on whether the project:
- was closed out prior to the current fiscal year
- was closed out during this fiscal year
- is projected to be closed out during the remainder of this fiscal year
- is projected to close out next fiscal year or beyond
Each of these cases is discussed in turn. Finally, you should also budget interim interest and debt
service payments for any new capital projects that have yet to be itemized in the Treasurer's Office
schedules, if you anticipate that such activity will occur during the five-year budget planning period.
Project Closed Out Prior to Current Fiscal Year
No interim interest is to be budgeted for next fiscal year. The amount of interest in the Internal Capital
Project Loan schedule for next year for that project represents a full year’s interest and should be budgeted,
along with any principal payment. These amounts should agree with the final amortization schedule distributed by the
Treasurer’s Office. The amounts shown on the Internal Capital Project Loan schedule should be budgeted for the
remainder of the five-year budget planning period as well.
Project Already Closed Out During This Fiscal Year
Interim interest to be credited or charged next July is the actual amount shown on the Interim Interest schedule
(also reflected in the General Ledger under the INTF Stat Object Code and the Program Code for the project) and should
be budgeted using the accounting flexfield indicated on that report. Alternatively, you may budget net interim interest
under Program 8999.
Project To Be Closed Out Before the End of This Fiscal Year
For projection purposes, the Treasurer’s Office has assumed that interest shown on the Interim Interest schedule thus
far through this fiscal year (matching the actual amount accumulated in the INTF Stat Object) will be charged or
credited at the beginning of next fiscal year, and that no further interim interest pertaining to the project will
be assessed. Consistent with this approach, the Treasurer’s Office has adjusted the amount of interest shown for
next fiscal year in the Internal Capital Project Loan schedule to reflect interest for balance of the current
fiscal year only. In effect, this assumes that the interim construction loan will convert to an amortizing loan
this fiscal year in the month following the last month for which interim interest was calculated.
For budgeting purposes, you should use the principal and interest amounts shown on both the Interim Interest and
Internal Capital Project Loan schedules.
Project To Be Closed Out Next Fiscal Year Or Thereafter
The Treasurer’s Office has provided interim interest amounts through a portion of this fiscal year only.
You should project any interim interest accretion for the balance of this year and future fiscal years – based on
anticipated expenditure and funding cash flows – for projects that you believe will remain open beyond this year and
include the appropriate interest amounts in your budget submission. You should also budget the principal and interest
amounts shown in the Internal Capital Project Loan schedule starting two years hence or beyond. (The Internal Capital
Project Loan schedule should not reflect any interest or principal payment in the next fiscal year, as amortization begins
in the fiscal year following the fiscal year of project closeout.)

|